This page details a list of permits obtained for the project, along with a construction schedule.
LIST OF PERMITS:
* Order of Conditions - obtained on November 21st 2024
* MEPA Review - EENF in the Environmental Monitor on February 26, 2025, SEIR anticipated to be in the Environmental Monitor on June 11, 2025 or June 25, 2025. Link here for further info.
* Chapter 91 - to be submitted Summer 2025.
* US Army Corps of Engineers General Permit - to be obtained prior to outfall installation.
* NPDES Construction General Permit - to be obtained prior to construction.
CONSTRUCTION TIMELINE:
* Start of Construction - Spring 2026
* Completion of Construction - Summer 2027
* Building/Site Open - Fall of 2027